Scope: The works under the contract included bulk earthworks, including the excavation and removal of excess spoil off site, drainage works including the installation of a Humes Stormtrap System, drainage cells, backfilling, testing and compaction.
The works were completed within the 3-week time frame provided by the client and within budget.
Client: Town of Bassendean